How to Apply for Net Metering in Pakistan 2026 — Step-by-Step Guide
What is Net Metering in Pakistan?
Net metering is a billing arrangement where your electricity meter runs backwards when your solar system generates more power than you use. The surplus units are exported to your DISCO’s grid and credited to your account at the retail tariff rate. At the end of each billing cycle, you pay only for your net consumption (imported units minus exported units).
Eligibility for Net Metering in Pakistan
- System capacity: 1kW to 1,000kW (1MW)
- System type: Grid-tied (on-grid) or hybrid solar systems
- Consumer categories: Residential, Commercial, Industrial, Agricultural
- Installer must be PPIB-enlisted
- Equipment must meet NEPRA-approved standards
Step-by-Step Application Process
- Install your solar system — Hire a PPIB-enlisted installer. Installation takes 1–3 days.
- Obtain NEPRA generation licence — Your installer applies for an NEPRA generation licence (systems under 25kW are exempt). Takes 2–4 weeks.
- Submit application to your DISCO — File the net metering application at your local DISCO office (LESCO, HESCO, FESCO, MEPCO, IESCO, PESCO, QESCO, GEPCO, or SEPCO) with all required documents.
- Technical inspection — DISCO engineers visit your site to inspect the installation. Typically within 7–21 days of application.
- Bidirectional meter installation — After approval, DISCO replaces your standard meter with a bidirectional meter. Cost: Rs 15,000–25,000 (borne by consumer).
- Net metering agreement signed — Sign the Net Metering Connection Agreement with the DISCO. Your system is now officially live.
Documents Required for Net Metering Application
| Document | Details |
|---|---|
| CNIC copy | Applicant’s national identity card |
| Electricity bill copy | Latest 3 months’ bills from your DISCO |
| PPIB registration / NOC | Your installer’s PPIB registration number |
| Single-line diagram (SLD) | Electrical diagram of your solar system — prepared by installer |
| Equipment specifications | Datasheet of panels and inverter with model numbers |
| Site photographs | Photos of installed panels, inverter, and metering location |
| Net metering application form | Available from DISCO office or their website |
Net Metering Costs (2026)
| Cost Item | Amount |
|---|---|
| Bidirectional meter | Rs 15,000–25,000 |
| PPIB registration fee (if required) | Rs 5,000–15,000 |
| Application processing fee | Rs 1,000–3,000 (varies by DISCO) |
| Total extra cost | Rs 20,000–40,000 |
How Long Does Net Metering Take in Pakistan?
From application submission to live net metering, the typical timeline is 4–8 weeks for residential consumers. LESCO (Lahore) and IESCO (Islamabad) tend to be faster (3–5 weeks). HESCO and QESCO may take up to 10–12 weeks.
Net Metering Tariff Rates in Pakistan 2026
Under NEPRA regulations, exported solar units are credited at the applicable retail tariff rate for your consumer category — approximately Rs 45–58/unit for domestic consumers. Units exported beyond your monthly consumption roll over as a monetary credit on your next bill.
Frequently Asked Questions
Check our Solar Panel Prices and System Size Guides to plan your system before installation.
Sources & references
Where this page states a rule, a tariff or a registration requirement, it comes from the documents below. Links go to the document itself, not a homepage. Prices on this page come from our own daily rate feed, not from these sources.
- NEPRA (Prosumer) Regulations, 2026 — notified 6 August 2026. Sets the framework that replaced straight net metering with net billing. Under it, a prosumer facility of 25 kW or below does not need concurrence from the Authority.
- NEPRA net-metering licences — the register of issued distributed-generation and net-metering licences.
- Checklist for enlistment of installers under the AEDB (Certification) Regulations, 2021 — the actual requirements an installer must meet. Note that AEDB was dissolved and merged into PPIB in July 2023, so enlistment is handled by PPIB, even though the regulations still carry the AEDB name.
- Your distribution company — LESCO, MEPCO, FESCO, GEPCO, IESCO, PESCO, QESCO, HESCO, SEPCO or K-Electric — for the tariff that applies to your area and the net-metering application itself. K-Electric runs its own process, separate from the DISCOs.
Regulatory links last checked 4 October 2026. Rules change; confirm current figures with the authority or a licensed installer before you commit money.