How to Apply for Net Metering in Pakistan 2026 — Step-by-Step Guide

How to Apply for Net Metering in Pakistan 2026 — Step-by-Step Guide

How to Apply for Net Metering in Pakistan 2026 — Step-by-Step Guide

Net metering allows solar system owners in Pakistan to sell surplus electricity back to the grid, dramatically reducing annual electricity bills. Under NEPRA’s net metering regulations (amended 2023), any residential or commercial consumer with a 1kW–1MW solar system can apply. This guide walks you through the entire process — documents, costs, timeline, and what to expect from your DISCO.

What is Net Metering in Pakistan?

Net metering is a billing arrangement where your electricity meter runs backwards when your solar system generates more power than you use. The surplus units are exported to your DISCO’s grid and credited to your account at the retail tariff rate. At the end of each billing cycle, you pay only for your net consumption (imported units minus exported units).

📊 Example: If you import 400 units from the grid and export 250 units from your solar system in a month, you are billed for only 150 net units — saving Rs 11,250–15,000 at current rates (Rs 45–60/unit).

Eligibility for Net Metering in Pakistan

  • System capacity: 1kW to 1,000kW (1MW)
  • System type: Grid-tied (on-grid) or hybrid solar systems
  • Consumer categories: Residential, Commercial, Industrial, Agricultural
  • Installer must be PPIB-enlisted
  • Equipment must meet NEPRA-approved standards

Step-by-Step Application Process

  1. Install your solar system — Hire a PPIB-enlisted installer. Installation takes 1–3 days.
  2. Obtain NEPRA generation licence — Your installer applies for an NEPRA generation licence (systems under 25kW are exempt). Takes 2–4 weeks.
  3. Submit application to your DISCO — File the net metering application at your local DISCO office (LESCO, HESCO, FESCO, MEPCO, IESCO, PESCO, QESCO, GEPCO, or SEPCO) with all required documents.
  4. Technical inspection — DISCO engineers visit your site to inspect the installation. Typically within 7–21 days of application.
  5. Bidirectional meter installation — After approval, DISCO replaces your standard meter with a bidirectional meter. Cost: Rs 15,000–25,000 (borne by consumer).
  6. Net metering agreement signed — Sign the Net Metering Connection Agreement with the DISCO. Your system is now officially live.

Documents Required for Net Metering Application

DocumentDetails
CNIC copyApplicant’s national identity card
Electricity bill copyLatest 3 months’ bills from your DISCO
PPIB registration / NOCYour installer’s PPIB registration number
Single-line diagram (SLD)Electrical diagram of your solar system — prepared by installer
Equipment specificationsDatasheet of panels and inverter with model numbers
Site photographsPhotos of installed panels, inverter, and metering location
Net metering application formAvailable from DISCO office or their website

Net Metering Costs (2026)

Cost ItemAmount
Bidirectional meterRs 15,000–25,000
PPIB registration fee (if required)Rs 5,000–15,000
Application processing feeRs 1,000–3,000 (varies by DISCO)
Total extra costRs 20,000–40,000

How Long Does Net Metering Take in Pakistan?

From application submission to live net metering, the typical timeline is 4–8 weeks for residential consumers. LESCO (Lahore) and IESCO (Islamabad) tend to be faster (3–5 weeks). HESCO and QESCO may take up to 10–12 weeks.

💡 Pro Tip: Submit your net metering application immediately after installation. Exported units before the bidirectional meter is installed are not credited.

Net Metering Tariff Rates in Pakistan 2026

Under NEPRA regulations, exported solar units are credited at the applicable retail tariff rate for your consumer category — approximately Rs 45–58/unit for domestic consumers. Units exported beyond your monthly consumption roll over as a monetary credit on your next bill.

Frequently Asked Questions

❓ Can I apply for net metering myself or do I need an installer?
In practice, your PPIB-enlisted installer handles most of the paperwork including the SLD, equipment specs, and the required documentation. You attend the DISCO office yourself for the formal application and agreement signing.
❓ Does a hybrid solar system qualify for net metering?
Yes. Both on-grid and hybrid solar systems are eligible for NEPRA net metering. The inverter must be grid-tied (not off-grid). Popular hybrid inverters like Growatt SPH, Huawei SUN2000, and Solis all support net metering.
❓ What happens to my exported units if I don’t use them?
Unused export credits roll forward to the next billing cycle as a monetary credit. At annual reconciliation, if credits remain unused, NEPRA regulations require DISCOs to pay you at the avoided cost rate for any remaining balance.
❓ Is net metering available in all cities of Pakistan?
Yes. All nine DISCOs in Pakistan are required under NEPRA regulations to offer net metering to eligible consumers. Processing times and procedures may vary by DISCO.
Planning to go solar and apply for net metering?

Check our Solar Panel Prices and System Size Guides to plan your system before installation.

Sources & references

Where this page states a rule, a tariff or a registration requirement, it comes from the documents below. Links go to the document itself, not a homepage. Prices on this page come from our own daily rate feed, not from these sources.

  • NEPRA (Prosumer) Regulations, 2026 — notified 6 August 2026. Sets the framework that replaced straight net metering with net billing. Under it, a prosumer facility of 25 kW or below does not need concurrence from the Authority.
  • NEPRA net-metering licences — the register of issued distributed-generation and net-metering licences.
  • Checklist for enlistment of installers under the AEDB (Certification) Regulations, 2021 — the actual requirements an installer must meet. Note that AEDB was dissolved and merged into PPIB in July 2023, so enlistment is handled by PPIB, even though the regulations still carry the AEDB name.
  • Your distribution company — LESCO, MEPCO, FESCO, GEPCO, IESCO, PESCO, QESCO, HESCO, SEPCO or K-Electric — for the tariff that applies to your area and the net-metering application itself. K-Electric runs its own process, separate from the DISCOs.

Regulatory links last checked 4 October 2026. Rules change; confirm current figures with the authority or a licensed installer before you commit money.

Abubaker Jalil
Written by

Abubaker Jalil

Abubaker Jalil is an electrical engineer and a graduate of the University of Engineering and Technology (UET) Peshawar. He tracks panel, inverter and battery prices across Pakistan's wholesale solar markets and writes the buying guides on this site. If a dealer has quoted you a figure that does not match what you see here, write to info@solarpricepakistan.com.pk and it gets checked.