UAE’s Mohammed bin Rashid Solar Park — What Pakistan Can Learn
The Mohammed bin Rashid Solar Park — Key Facts
| Metric | Detail |
|---|---|
| Location | Saih Al-Dahal, Dubai — 50km south of city center |
| Total Target Capacity | 5,000 MW (5 GW) — completion by 2030 |
| Installed Capacity (2026) | ~2,850 MW operational |
| Technologies Used | Mono PERC / TOPCon PV, concentrated solar power (CSP), thermal storage |
| Lowest Solar Tariff Achieved | $0.0169/kWh (Phase 5, 2020) — world record at time |
| Developer Model | DEWA (government utility) + competitive IPP tenders |
| Investment | AED 50 billion (~$14 billion USD) |
| Land Area | 214 km² total planned area |
How Dubai Got Solar to $0.017/kWh
The most remarkable achievement of the MBRS Solar Park is its electricity tariff. Phase 5 (900MW) received bids as low as $0.0169/kWh from a consortium led by ACWA Power and LONGi — making it the cheapest electricity ever produced in the Middle East at the time. How?
- Competitive tender process: DEWA ran transparent international competitive auctions attracting global developers — driving prices down through genuine competition
- Creditworthy off-taker: DEWA is a AAA-rated utility backed by the Dubai government. Developers accepted razor-thin margins because payment risk was zero
- Long-term PPAs: 25-year power purchase agreements allowed developers to finance at extremely low interest rates — debt cost is the biggest factor in solar tariff
- Massive scale: 900MW in a single phase allowed procurement at maximum economies of scale for panels, inverters, and balance-of-system
- Desert site with high irradiance: Dubai’s 5.5–6.0 kWh/m²/day solar resource (similar to Pakistan’s Balochistan) maximizes generation per installed MW
Comparison: Pakistan’s Solar Resource vs Dubai
| Location | Solar Irradiance (kWh/m²/day) | vs Dubai |
|---|---|---|
| Dubai (MBRS Solar Park) | 5.5–6.0 | Baseline |
| Balochistan (Quetta/Turbat) | 6.0–7.0 | Better |
| Bahawalpur / Cholistan | 5.8–6.5 | Similar to better |
| Karachi coast | 5.5–6.0 | Similar |
| Lahore / Multan | 5.0–5.5 | Slightly lower |
Pakistan’s Balochistan has better solar irradiance than Dubai. The fundamental resource for achieving Dubai-level solar tariffs exists in Pakistan. The gap is in project execution, financing, and policy — not physics.
5 Lessons Pakistan Must Apply
- Creditworthy off-taker is everything: Pakistan’s circular debt and DISCO payment record deters low-cost financing. Until off-taker credit risk is resolved, Pakistan cannot achieve Dubai-level tariffs regardless of solar resource quality
- Transparent competitive tenders get the best prices: DEWA’s international competitive auctions were open, transparent, and attracted global competition. Pakistan’s procurement history has been less transparent, limiting competition
- Scale matters: Pakistan should tender 500MW–1GW+ projects, not 50–100MW — scale drives down per-unit costs dramatically
- CSP + thermal storage for 24-hour power: MBRS Solar Park includes concentrated solar power (CSP) with molten salt thermal storage — providing solar electricity at night. Pakistan’s baseload reliability problem could be addressed similarly at large desert sites
- Land bank early: Dubai identified and cleared land years before projects broke ground. Pakistan needs a designated solar land bank in Balochistan and Cholistan with clear titles, grid connection plans, and environmental clearances ready for developers
Frequently Asked Questions
⚡ Pakistan’s rooftop solar revolution starts now
Sources & references
Tariff, net-metering, and policy details on this page draw on the following official sources. Rates change often, so confirm current figures with the relevant authority or a licensed installer before you decide.
- NEPRA — National Electric Power Regulatory Authority: electricity tariffs and the 2026 shift from net metering to net billing.
- AEDB — Alternative Energy Development Board: solar policy, installer standards, and net-metering guidance.
- Your local distribution company (DISCO) — for example LESCO, K-Electric, IESCO, MEPCO, PESCO or QESCO — for area-specific tariffs and the net-metering application process.







