How Solar Net Metering Billing Works in Pakistan — Simply Explained
The Basic Concept
With net metering, your electricity meter measures two things: units you consume from the grid (import) and units your solar system exports to the grid (export). At the end of the billing period, your DISCO subtracts your exports from your imports. You pay only for the net difference — hence “net metering.”
How the Bill Calculation Works
| Item | Example |
|---|---|
| Units imported from grid this month | 350 kWh |
| Units exported to grid from solar | 280 kWh |
| Net units billed (import − export) | 70 kWh |
| Applicable tariff slab | 101–200 unit rate (Rs. 10.06/kWh) |
| Energy charges | 70 × Rs. 10.06 = Rs. 704 |
| Fixed charges + taxes (remain) | ~Rs. 1,500 |
| Total bill | ~Rs. 2,204 |
The Quarterly Adjustment — Critical to Understand
Pakistan’s net metering policy has an important nuance: if your exports exceed your imports in a given month, the surplus is carried forward as a credit to the next month. However, at the end of each quarter, any remaining credit is purchased by the DISCO at the Avoided Cost Rate — which is significantly lower than the import tariff you pay.
Step-by-Step: What Happens Each Billing Cycle
- Your bidirectional (net metering) meter records both import and export kWh separately
- At your billing date, the DISCO meter reader records both figures
- The DISCO calculates net units: imports minus exports
- If net is positive (imported more than exported), you pay for net units at applicable slab rate
- If net is negative (exported more than imported), the surplus credit carries to next month
- At quarter end, accumulated export surplus is settled at Avoided Cost Rate — you receive credit on next bill
The Net Metering Connection Process
- Install PPIB-certified solar system with DISCO-accepted inverter
- Submit net metering application to your local DISCO (LESCO, HESCO, MEPCO, etc.) with installation certificate, single-line diagram, and system specs
- DISCO conducts a site inspection (typically 4–8 weeks after application)
- DISCO installs the bidirectional meter (at applicant’s cost — Rs. 15,000–25,000)
- Net metering activation — usually 2–4 weeks after meter installation
Frequently Asked Questions
⚡ Start your net metering journey
Sources & references
Where this page states a rule, a tariff or a registration requirement, it comes from the documents below. Links go to the document itself, not a homepage. Prices on this page come from our own daily rate feed, not from these sources.
- NEPRA (Prosumer) Regulations, 2026 — notified 6 August 2026. Sets the framework that replaced straight net metering with net billing. Under it, a prosumer facility of 25 kW or below does not need concurrence from the Authority.
- NEPRA net-metering licences — the register of issued distributed-generation and net-metering licences.
- Checklist for enlistment of installers under the AEDB (Certification) Regulations, 2021 — the actual requirements an installer must meet. Note that AEDB was dissolved and merged into PPIB in July 2023, so enlistment is handled by PPIB, even though the regulations still carry the AEDB name.
- Your distribution company — LESCO, MEPCO, FESCO, GEPCO, IESCO, PESCO, QESCO, HESCO, SEPCO or K-Electric — for the tariff that applies to your area and the net-metering application itself. K-Electric runs its own process, separate from the DISCOs.
Regulatory links last checked 4 October 2026. Rules change; confirm current figures with the authority or a licensed installer before you commit money.



