How Solar Net Metering Billing Works in Pakistan — Simply Explained

Solar Net Metering Billing Pakistan

How Solar Net Metering Billing Works in Pakistan — Simply Explained

Net metering is the system that allows Pakistani solar owners to export surplus electricity to the WAPDA grid and receive credit on their bill. Many buyers install solar without fully understanding how net metering billing works — leading to surprises when bills arrive. This guide explains exactly how solar net metering billing Pakistan works — how units are counted, billed, and credited.

The Basic Concept

With net metering, your electricity meter measures two things: units you consume from the grid (import) and units your solar system exports to the grid (export). At the end of the billing period, your DISCO subtracts your exports from your imports. You pay only for the net difference — hence “net metering.”

How the Bill Calculation Works

ItemExample
Units imported from grid this month350 kWh
Units exported to grid from solar280 kWh
Net units billed (import − export)70 kWh
Applicable tariff slab101–200 unit rate (Rs. 10.06/kWh)
Energy charges70 × Rs. 10.06 = Rs. 704
Fixed charges + taxes (remain)~Rs. 1,500
Total bill~Rs. 2,204

The Quarterly Adjustment — Critical to Understand

Pakistan’s net metering policy has an important nuance: if your exports exceed your imports in a given month, the surplus is carried forward as a credit to the next month. However, at the end of each quarter, any remaining credit is purchased by the DISCO at the Avoided Cost Rate — which is significantly lower than the import tariff you pay.

⚠️ The import vs export rate gap: You pay Rs. 26–35/kWh to import electricity. WAPDA buys your surplus at the Avoided Cost Rate — approximately Rs. 14–19/kWh in 2026. This 40–50% rate gap means over-generating and exporting large surpluses gives poor returns. Size your system to cover your own consumption, not to export large surpluses.

Step-by-Step: What Happens Each Billing Cycle

  1. Your bidirectional (net metering) meter records both import and export kWh separately
  2. At your billing date, the DISCO meter reader records both figures
  3. The DISCO calculates net units: imports minus exports
  4. If net is positive (imported more than exported), you pay for net units at applicable slab rate
  5. If net is negative (exported more than imported), the surplus credit carries to next month
  6. At quarter end, accumulated export surplus is settled at Avoided Cost Rate — you receive credit on next bill

The Net Metering Connection Process

  1. Install PPIB-certified solar system with DISCO-accepted inverter
  2. Submit net metering application to your local DISCO (LESCO, HESCO, MEPCO, etc.) with installation certificate, single-line diagram, and system specs
  3. DISCO conducts a site inspection (typically 4–8 weeks after application)
  4. DISCO installs the bidirectional meter (at applicant’s cost — Rs. 15,000–25,000)
  5. Net metering activation — usually 2–4 weeks after meter installation

Frequently Asked Questions

❓ How long does net metering approval take in Pakistan?
Total time from application to activation ranges from 6 weeks to 6 months depending on your DISCO and region. LESCO (Lahore) typically takes 8–16 weeks. HESCO (Hyderabad/Sindh) and MEPCO (Multan) have historically been slower. The biggest delays are in meter installation after inspection approval. Your solar system works as a self-consumption off-grid/hybrid system while net metering is pending — you don’t need net metering to use solar, only to get credit for exports.
❓ What is the maximum solar system size for net metering in Pakistan?
NEPRA allows net metering for systems up to the consumer’s sanctioned load (the maximum load on your electricity connection). Standard domestic connections in Pakistan typically have a 5–10 kW sanctioned load. You can apply to increase your sanctioned load to accommodate a larger solar system, though this involves additional DISCO fees and connection upgrade work.
❓ Can I do net metering without a hybrid inverter?
Yes — net metering works with grid-tied (string) inverters as well as hybrid inverters. The key requirement is that your inverter is PPIB-certified and grid-sync capable. String inverters export 100% of surplus directly; hybrid inverters store surplus in batteries first and only export what batteries can’t absorb. For maximum net metering exports, a string inverter with no battery is most straightforward. For load shedding backup, hybrid with battery is better.
❓ Will my WAPDA bill go to zero with solar net metering?
Your energy charges can go to near-zero or even result in a credit if your system generates more than you consume. However, your bill will never be truly zero — fixed charges (meter rent, minimum charges), electricity duty, and GST remain payable even with zero net consumption. Expect a minimum bill of Rs. 500–1,500/month even with a perfectly sized solar system.

⚡ Start your net metering journey

Net metering complete guide →  |  6kW system prices →

Sources & references

Where this page states a rule, a tariff or a registration requirement, it comes from the documents below. Links go to the document itself, not a homepage. Prices on this page come from our own daily rate feed, not from these sources.

  • NEPRA (Prosumer) Regulations, 2026 — notified 6 August 2026. Sets the framework that replaced straight net metering with net billing. Under it, a prosumer facility of 25 kW or below does not need concurrence from the Authority.
  • NEPRA net-metering licences — the register of issued distributed-generation and net-metering licences.
  • Checklist for enlistment of installers under the AEDB (Certification) Regulations, 2021 — the actual requirements an installer must meet. Note that AEDB was dissolved and merged into PPIB in July 2023, so enlistment is handled by PPIB, even though the regulations still carry the AEDB name.
  • Your distribution company — LESCO, MEPCO, FESCO, GEPCO, IESCO, PESCO, QESCO, HESCO, SEPCO or K-Electric — for the tariff that applies to your area and the net-metering application itself. K-Electric runs its own process, separate from the DISCOs.

Regulatory links last checked 4 October 2026. Rules change; confirm current figures with the authority or a licensed installer before you commit money.

Abubaker Jalil
Written by

Abubaker Jalil

Abubaker Jalil is an electrical engineer and a graduate of the University of Engineering and Technology (UET) Peshawar. He tracks panel, inverter and battery prices across Pakistan's wholesale solar markets and writes the buying guides on this site. If a dealer has quoted you a figure that does not match what you see here, write to info@solarpricepakistan.com.pk and it gets checked.